Once it
is decided to build a reservoir on a river by constructing a dam
across it, it is necessary to arrive at a suitable design capacity of
the reservoir. As has been discussed, the reservoir storage generally
consists of there main parts
which may
be broadly classified as:
1.
Inactive storage including dead storage
2. Active storage, and
3. Flood
and surcharge storage.
In
general, these storage capacities have to be designed based on
certain specified considerations, which have been discussed
separately in the following Bureau of Indian Standard codes:
IS: 5477 Fixing the capacities of reservoirs- Methods
IS: 5477 Fixing the capacities of reservoirs- Methods
(Part 1):
1999 General requirements
(Part 2):
1994 Dead storage
(Part 3):
1969 Line storage
(Part 4):
1911 Flood storage
The data
and information required for fixing the various components of the
design capacity of a reservoir are as follows:
a)
Precipitation, run-off and silt records available in the region;
b)
Erodibility of catchment upstream of reservoir for estimating
sediment yield;
c) Area
capacity curves at the proposed location;
d) Trap
efficiency;
e) Losses
in the reservoir;
f) Water
demand from the reservoir for different uses
g)
Committed and future upstream uses;
h)
Criteria for assessing the success of the project;
i)
Density current aspects and location of outlets;
j) Data
required for economic analysis; and
k) Data
on engineering and geological aspects.
These
aspects are explained in detail in the following sections.
(a)
Precipitation, Run-Off and Silt Record
The
network of precipitation and discharge measuring stations in the
catchment upstream and near the project needs to be considered to
assess the capacity of the same to adequately sample both spatially
and temporally the precipitation and the stream flows.
The
measurement procedures and gap filling procedures in respect of
missing data as also any rating tables or curves need to be
critically examined so that they are according to guidelines of World
Meteorological Organization (WMO). Long-term data has to be checked
for internal consistency between rainfall and discharges, as also
between data sets by double mass analysis to highlight any changes in
the test data for detection of any long term trends as also for
stationarity. It is only after such testing thatthe data should be
used for generating the long term inflows of water (volumes in 10
days, 15 days, monthly or yearly inflow series) into the reservoir.
Sufficiently
long term precipitation and run-off records are required for
preparing the water inflow series. For working out the catchment
average sediment yield, long-term data of silt measurement records
from existing reservoirs are essential. These are pre-requisites for
fixing the storage capacity of reservoirs.
If long
term run-off records are not available, concurrent rainfall and
run-off data may be used to convert long term rainfall data (which is
generally available in many cases) into long-term run-off series
adopting appropriate statistical/conceptual models. In some cases
regression analysis may also be resorted to for data extension.
(b)
Estimation of average Sediment Yield from the catchment area above
the reservoir
It is
usually attempted using river sediment observation data or more
commonly from the experience of sedimentation of existing reservoirs
with similar characteristics. Where observations of stage/flow data
is available for only short periods, these have to be suitably
extended with the help of longer data on rainfall to estimate as far
as possible sampling errors due to scanty records. Sediment discharge
rating curve may also be prepared from hydraulic considerations using
any of the standard sediment load formulae, such as, Modified
Einstein’s procedure, Young’s stream power, etc. It is also
necessary to account for the bed load which may not have been
measured. Bed load measurement is preferable and when it is not
possible, it is often estimated as a percentage generally ranging
from 5 to 20 percent of the suspended sediment load. However, actual
measurement of bed load needs to be undertaken particularly in cases
where high bed loads are anticipated. To assess the volume of
sediment that would
deposit
in the reservoir, it is further necessary to make estimates of
average trap efficiency of the reservoir and the likely unit weight
of sediment deposits, along with time average over the period
selected. The trap efficiency would depend on the capacity inflow
ratio but would also vary with the locations of controlling outlets
and reservoiroperating procedures. Computations of reservoir trap
efficiency may be made using the trap efficiency curves such as those
developed by Brune and by Churchill (see IS: 12182-1987).
(c)Elevation
Area Capacity Curves
Topographic
survey of the reservoir area should form the basis for obtaining
these curves, which are respectively the plots of elevation of the
reservoir versus surface area and elevation of the reservoir versus
volume. For preliminary studies, in case suitable topographic map
with contours, say at intervals less than 2.5 m is not available,
stream profile and valley cross sections taken at suitable intervals
may form the basis for computing the volume. Aerial survey may also
be adopted when facilities are available.
(d)
Trap Efficiency
Trap
efficiency of reservoir, over a period, is the ratio of total
deposited sediment to the total sediment inflow. IS 12182 cover
relationship between sedimentation index of the reservoir and
percentage of incoming sediment and presenting curves may be used for
calculation of trap efficiency.
(e)
Losses in Reservoir
Water
losses mainly of evaporation and seepage occur under pre-project
conditions and are reflected in the stream flow records used for
estimating water yield. The construction of new reservoirs and canals
is often accompanied by additional evaporation and infiltration.
Estimation of these losses may be based on measurements at existing
reservoirs and canals. The measured inflows and outflows and the rate
of change of storage are balanced by computed total loss rate. The
depth of water evaporated per year from the reservoir surface may
vary from about 400 mm in cool and humid climate to more than 2500 mm
in hot and arid regions. Therefore, evaporation is an important
consideration in many projects and deserves careful attention.
Various methods like water budget method, energy budget method, etc
may be applied for estimating the evaporation from reservoir.
However, to be more accurate, evaporation from reservoir is estimated
by using data from pan-evaporimeters or pans exposed to atmosphere
with or without meshing in or near the reservoir site and suitably
adjusted. Seepage losses from reservoirs and irrigation canals may be
significant if these facilities are located in an area underlain by
permeable strata. Avoidance in full or in part of seepage losses may
be very expensive and technical difficulties involved may render a
project unfeasible. These are generally covered under the conveyance
losses in canals projected on the demand side of simulation studies.
(f)
Demand, Supply and Storage
The
demand should be compared with supplies available year by year. If
the demand is limited and less than the available run-off, storage
may be fixed to cater to that particular demand which is in excess of
the run-off. The rough and ready method is the mass curve method for
initial sizing. Even while doing the above exercise, water use data
are needed to assess the impact of human activities on the natural
hydrological cycle. Sufficient water use information would assist in
implementing water supply projects, namely, evaluating the
effectiveness of options for demand management and in resolving
problems inherent in competing uses of water, shortages caused by
excessive withdrawal, etc. Water demands existing prior to
construction of a water resource project should be considered in the
design of project as failure to do so may result in losses apart from
legal and social problems at the operation stage.
(g)
Committed and future upstream uses
The
reservoir to be planned should serve not only the present day
requirements but also the anticipated future needs. The social,
economic and technological developments may bring in considerable
difference in the future needs/growth rate as compared to the present
day need/growth rate. Committed and upstream future uses should also
be assessed in the same perspective.
(h)
Criteria for assessing the success of the project
Water
Resources Projects are to be designed for achieving specified
success. Irrigation projects are to be successful for 75 percent
period of simulation. Likewise power projects and water supply
projects are to be successful for 90 percent and nearly 100 percent
period of simulation respectively.
(i)
Density Current aspects and location of outlets
Density
current is defined as the gravitational flow of one fluid under
another having slightly different density. The water stored in
reservoir is generally free from silt but the inflow during floods is
generally muddy. There are, thus two layers having different
densities resulting in the formation of density currents. The density
currents separate the water from the clearer water and make the
turbid water flow along the river bottom. The reservoir silting rate
can be reduced by venting the density currents by properly locating
and operating the outlets and sluice ways.
(j)
Data Required for Economic Analysis
Economic
Analysis is carried out to indicate the economic desirability of the
project. Benefit cost ratio, Net benefit, Internal Rate of Return are
the parameters in this direction. It is desirable to have the benefit
cost ratio in the case of irrigation projects and flood mitigation
projects to be above 1.5 and 1.1 respectively. Benefit functions for
reservoir and water utilisation for irrigation, power, water supply
etc., are also to be determined judiciously. Cost benefit functions
are obtained as continuous functions using variable cost/benefit
against reservoir storage/net utilisation of water and from benefit
functions the benefit from unit utilisation of water can be
determined. The spillway capacity has to be adequate to pass the
inflow design flood using moderation possible with surcharge storage
or any other unobstructed capacity in the reservoir without
endangering the structural safety as provided elsewhere in the
standard. In the event of the inflow design flood passing the
reservoir, the design needs to ensure that dam break situation does
not develop or induce incremental damage downstream.
(k)
Data on Engineering and Geological Aspects
Under
engineering and geological aspects the following items of work shall
invariably be
carried
out:
i)
Engineering
1)
Preliminary surveys to assess the catchment and reservoir,
2)
Control surveys like topographical surveys,
3)
Location of nearest Railway lines/Roads and possible access, and
4)
Detailed survey for making area capacity curves for use in reservoir
flood routing.
ii)
Geology
1)
General formations and foundation suitability;
2)
Factors relating to reservoir particularly with reference to water
tightness;
3)
Contributory springs;
4)
Deleterious mineral and salt deposits; and
5)
Location of quarry sites, etc.
Source: CE, IIT Kharagpur